Project: RANS21RB   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Randall Brooks   -  
Project:   Rans - S-21 Outbound   -   VIEW REPORTS
Total Hours:1990
Total Flight Time:
Start/Last Date:Apr 03, 2021 - No Finish Date
Engine:Titan IO-340 180HP
Propeller:Whirlwind
 
Friendly URL: https://eaabuilderslog.org?s=RANS21RB

Home or Last Project Picture

Apr 20, 2023     Spinner install and first engine motoring - (4 hours)       Category: Fuselage
Removed spinner, prop, hub, spinner back plate. Measured and drilled spinner w/ #40 at required spacing. Match drilled spinner back plate. Opened holes for #11 screws. Drilled and installed nutplates in backplate. Reinstalled all back on engine. .Spinner fits perfectly. Gap around prop blades is good. Filled engine sump with 8qts. Phillips XC 20W50 oil. Removed bottom plugs and hand pulled prop thru about 20 times. Motored engine for 15 sec cycles allowing cool down between cycles. Oil pressure came up on second cycle to 52 psi. Motored 2 more cycles. No leaks noted.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.